MAINTENANCE
FN180/FN120 07/12 Maintenance Section 5-6
© 2012 Alamo Group Inc.
MAINTENANCE
DRIVELINES
The Drivelines and U-Joints should be inspected each morning before the Cutter is started. MntP-R-0456 and
Mnt-R-0457.
The U-Joint and CV Joint on the Driveline undergo extreme forces when the unit is turning or when the Wings
are being raised. It is important that the U-Joints and CV Joint be greased each day before the unit is started.
The U-Joints are located at each end of the Center and Wing Drivelines. The CV Joint is located at the end of
the Main Driveline. The U-Joint and CV Joint assemblies are accessible by rotating the Driveline Safety Shield
until the hole in the Shield matches up with the Grease Fitting. Use N.L.G.I. #2 Bearing Grease for lubrication.
Inspect the U-Joint for wear by holding the shaft on one side of the U-Joint while trying to rotate the shaft on the
other side of the U-Joint. If there is noticeable movement in the Driveline replace the U-joint before it causes
severe damage to the Driveline.
STANDARD EXTENDED LUBE LEVER
LOCATION INTERVAL INTERVAL ACTION PUMPS
Cross & Bearings * 8 Hours 50 Hours 2 - 3
Telescoping Members 8 Hours 50 Hours 8 - 10
CV Ball & Socket (80º CV) * 8 Hours 50 Hours 4 - 6
CV Center Housing (80º CV) 24 Hours 50 Hours 12 - 15
CE & Non-Rotating Guard Bushings 8 Hours 50 Hours 2
(1000 RPM MAX.)
* Constant Angle applications may require a Lube Interval of 4 hours.
ROTATING GUARD BUSHINGS SHOULD BE LUBRICATED UPON REPLACEMENT
80º CV DRIVELINE
TELESCOPING DRIVELINE